Complaint
- Complaint number
- NTB-000-384
- NTB Type
- 7.9. Inadequate trade related infrastructure
- Complaint
- Drivers crossing through Tete bridge take 2-3 days of waiting to cross in both directions of the route.
- Status note
- At the 9th meeting of the SADC Sub-committee on trade facilitation, Mozambique reported that following completion of construction works, Tete bridge is now fully operational. There are no more delays at the Bridge since construction works have been completed
- Progress update note
- Policy or regulatory NTB
- No
- Location
- Mozambique: Tete Bridge (Other)
- Reporting Country or Region
- Malawi
- Country specific trade issue
- No
- Date of incident
- 2010-08-11
- Status
- Resolved
- Date of resolution
- 2011-07-28
- Product Description
-
All products
- Total value
- 0
- Date reported
- 2010-08-11 00:00
- Modified
- 2011-07-28 23:15