Non-Tariff Measure

NTM classification
P13: Production and post-production requirements to export 
Date when the measure came into force
28 December 2007 
Publication where the measure is specified
Electricity Act 
Regulation where the measure is specified
Electricity Act 
Country/Region applying the measure
Malawi 
The rationale of the measure
No specific objective stated 
Coded list of objectives
X: For purposes n.e.s. 
Description of the measure
"3. Electricity supply activities to be carried on under licence
(1) No person shall carry on or be engaged in any manner in any activity for the supply of electricity, including the export of electricity from, and import of electricity into, Malawi, without a generation, transmission, importation, exportation or distribution
licence, as the case may be, issued by the Authority.
(3) Apart from the transmission licensee no other licensee shall be licensed to import or export power into and out of Malawi, respectively:
Provided that a distribution licensee may be licensed to export power out of
Malawi if such export is through a distribution line, and provided further that export of power shall not affect the local capacity to meet the demand for power at any time." 
Reference of the measure
Article 3 
Measure also domestic
No 

Products affected by the measure.

Code Product Partial coverage Partial coverage indication Date in Date out
2716.00.00 Electrical energy. (optional heading) kwh No    
Description
Electric energy 

Countries/Regions affected by the measure.

Inclusion/Exclusion Country Date in Date out
Inclusion Entire world    
Description
Entire world